Meme and I found some nice items at a local garage sale. I picked up this wrought iron table base for $8. The table will go somewhere in one of our outside rooms.
Monday, August 17, 2009
Garage Sales
Posted by Mark at 4:54 PM 1 comments
Sunday, August 16, 2009
Phase 2 Begins
Now that the designer, Meme, has found a picture of what she wants the seating wall to look like we can proceed with hardscape for phase 2 of this project.

Posted by Mark at 12:38 PM 0 comments
Tuesday, August 11, 2009
Phase 1 Finished
Coco and Andrew moved 5 tons of crushed granite and finished the hardscape on phase 1.
Andrew did most of the moving so that Coco would not have the big one.
Meme washed down the rock to remove dust and help it to begin to settle.
Then we did some staging and Andrew took some nice photos.
We move on to phase 2.
Posted by Mark at 3:39 PM 0 comments
Sunday, August 9, 2009
You too can do it
Meme makes the plan and Coco does the research. Materials needed include graph paper, straight edge, pencil, web access and good reference book/idea book.
Coco levels the site and builds one form and begins to experiment with pouring pads. Materials needed incude plywood, 2"x4"x8' studs, long drywall screws, rebar, wheel barrow,
shovels, pick axe, power driver and power miter. Andrew helps with these tasks and his only requirement is that he be in charge. Be sure to check the form for dimensions and squareness prior to the pour and allow enough
time for curing.